PREPARATIONS
Once the approvals and paperwork were completed, work on the towers began. Olshan's crews spent six weeks preparing the structures and surrounding site for blasting.

To their disappointment, the outer bands of hurricane Floyd blew in just four days before the scheduled event, and it was decided that the most critical preparatory activities would have to be postponed. It was too dangerous to perform the final cutting with high winds.
Several days later, the weather finally cleared and a new blast date was set.

Olshan’s team of burners meticulously began cutting dozens of small windows in supporting steel columns as laid out in the demolition plan. Once all burning was completed, Dykon began the task of attaching more than 400 linear shape charges to specific beams and columns throughout the towers.
The smaller Umbilical Tower was loaded first. Explosives would be used to remove the bottom four feet along the south end of the structure, allowing it to roll over.

Next came the loading of the Mobile Service Tower. An interesting feature of the MST was that it literally ‘moved’ back and forth on a set of railroad tracks to facilitate the servicing of rockets while they rested on the launch pad. As part of this unique design, the bottom level of the structure consisted of massive X-braces instead of the conventional beam-and-column construction ordinarily found at the base of large steel towers.

Due to this unusual framing, it was decided that the structure would be blasted on a slightly higher level, just above the heavily reinforced X-braces.
 
As per the blast plan, a ‘wedge’ - starting 15 feet tall along the front side of the MST and tapering down towards the rear - was targeted for explosive removal. A review of a $57 million dollar renovation program completed in 1989 found that most of the structure had been retrofitted with additional steel plates on the flanges of the columns. Large shaped charges had to be placed opposite each other in order to cut through these multi-plated steel flanges.
Once the explosives were attached, Olshan’s crews installed protective plywood boxes around the shaped charges and wrapped the boxes with conveyor belting. The boxes and belting would help contain debris created by the detonation.
Bad weather complicated Olshan's already-tight preparation schedule, which resulted in some long days - and nights - leading up to the blast.
Because Florida is the lightning capital of the world, a non-electric system of initiation was selected for the project. This system would provide the greatest safety against premature detonation due to lightning strikes, stray electricity or radio interference.

Dykon then carefully began placing the timing mechanisms that would guide the towers into their designated fall zones.
The Mobile Service Tower had two large Lightning Diffusor towers on either side of the fall zone that Lockheed Martin needed to save. Therefore, the direction of fall was absolutely critical. Additionally, the launch pad’s massive concrete slabs were slated for reuse with the new Atlas system, so Olshan took the labor-intensive measure of placing over five feet of sand throughout the impact area of each structure. (Such precautions are often implemented to help absorb the ‘ground-slap’ that occurs when felling tall, heavy structures such as communication towers or smokestacks.)
A field inspector is dwarfed by one of the twelve lightning diffusor footings located near the blast zonee
Both Olshan and Dykon retained the services of Protec Documentation Services to perform detailed inspections of nearby structures prior to the blast. Protec's field representatives spent several days surveying a wide wariety of structures – including fuel farms, oxygen tanks and support buildings among dozens of other items to document any changes that might occur as a result of the project.
Several weeks earlier, the firm had worked with Dykon to formulate a detailed impact-calculation study for the project, and had submitted independent rail-elevation surveys for the Mobile Service Tower.

Protec's final responsibility was to install and operate seismographs at key points around the site. Technicians programmed these instruments to monitor vibration levels from both the initial explosive detonation as well as the resulting ground impact.
CLICK ON A LINK BELOW TO CONTINUE

Apartment Buildings | Bridges | Conveyors | Hospitals | Hotels | Manufacturing Plants
Office Buildings | Powerhouses | Public Housing | Retail Buildings | Silos & Containers
Smokestacks & Chimneys | Sports & Entertainment Venues | Towers
Storage Facilities & Warehouses | Unique & Wacky Grab-Bag

  Enter your E-mail address below,
  and we'll keep you informed on site
  updates and future live events.