Razing the Roof of Welsh Civic Auditorium

Dykon performs impressive blast at historic entertainment venue

Over the past several years, large cities throughout America and the United Kingdom have experienced a renaissance in entertainment facility upgrades, which in turn has led to the demolition of many outdated sports and concert venues.

While these high-profile projects require the destruction and removal of large volumes of material, most present few unique demolition challenges. By the nature of their use, the facilities themselves are often surrounded by a sea of parking lots and open space, and the largest concern facing a general contractor usually involves a time deadline and the need to efficiently manage his team's operations.

Every now and then, however, one of these venues is located squarely in the heart of a major urban city, and its safe demise allows for nothing less than a precisely coordinated, delicate effort from a seasoned team of demolition veterans. Such was the case recently in Grand Rapids, Michigan USA when demolition specialists at Pitsch Companies, Grand Rapids, and Dykon Explosive Demolition, Tulsa, Oklahoma were contracted to fell the 2.3 million pound roof of the Welsh Civic Auditorium.

Constructed in 1932 as the art-deco centerpiece of Grand Rapids, the Welsh Civic Auditorium hosted hundreds of Big Band concerts during the first half of the century, and later welcomed the likes of Simon and Garfunkel and Johnny Cash among a long list of top-name performers. The facility closed on June 1, 2003 to allow for a $220 million renovation project designed to convert the interior into a ballroom for the DeVos Place Convention Center, which shares a wall with the existing auditorium. The Welsh's original limestone facades and lobby were also to be kept intact.

Dykon president Jim Redyke devised a blast plan to drop the 70-year-old, 180-foot by 130-foot steel truss roof straight down onto the building's pre-stressed concrete floor using 14 pounds of RDX linear shaped explosive charges on a single delay. Redyke's plan also called for meticulous preparatory operations such as saw-cutting a three-foot wide gap around the perimeter of the structure's basement slab (to help mitigate the transmission of ground vibration) and covering the closest adjacent windows and doorways with protective plywood panels and geotextile fabric. These activities were completed on a strict timeline under the direct supervision of Pitsch Vice President, Gary Pitsch.

As an added measure of security, project officials contracted Protec Documentation Services, Hainesport, New Jersey, to forecast and calculate ground vibration and airblast levels prior to the demolition. The team also performed detailed pre-blast inspections of various structures surrounding the site, including the four-star Grand Plaza Hotel and the existing auditorium lobby located ten feet from the roof's closest point of impact.

The blast was scheduled for 3:00pm on a Saturday afternoon so as not to interfere with business activities or nearby church services. Thousands of local residents who had lined up along nearby rooftops and the banks of the Grand River then watched and cheered as a single sharp explosion brought the giant steel trusses down within a majestic swirl of dust, directly onto their intended zone. Following the blast, it was confirmed that all adjacent buildings remained unharmed, and vibration levels recorded at various locations were slightly less than predicted.

  Enter your E-mail address below,
  and we'll keep you informed on site
  updates and future live events.